Home Africa FG sets aside $1.61bn for 24-hour power supply, Says TCN

FG sets aside $1.61bn for 24-hour power supply, Says TCN

by CredibleNews

Managing Director, Transmission Company of Nigeria, TCN, Alhaji Usman Gur, said the federal government in collaboration with international donor agencies has set aside over $1.61 billion to ensure constant power supply.

Gur, who is also the Chief Executive Officer of TCN, revealed this yesterday in Kano while briefing newsmen at Kumbotso power sub-station.

According to him, the project will be carried out under the Transmission Rehabilitation Expansion Programme.

“We are rehabilitating and expanding to degree 20,000 megawatts by 2022 across the country,” he said.

He noted that the federal government has already earmarked N32 billion to compensate Nigerians whose lands, houses and farms would be affected by the right-of-way to create power lines for the execution of the project.

“The total amount that we are going to pay for compensation across the country is about N32 billion and the total project cost is $1.61 billion. The project will be supported by various international donors.

“The compensation for right-of-way from Kumbotso sub-station to Zagara will cost about N3 billion. We have not completely validated it. The total cost for compensation across the country is being provided by the federal government,” he said.